Builder: Stadtwerke Munster-Bispingen GmbH
Location: Munster-Bispingen
Mountain formation:Loose formations
Drilling method:Air lifting drill
RKR core drilling
Number of holes: 1
Drilling depth in m: 107
Total drilling meters: 107
Drilling Ø in mm: 800
Expansion data: DN 400 / VA / KV
Purpose of the drilling:
Delivery of 1 piece. Test well for a planned new WW. In advance, an AB was sunk to 64.00 m below GOK using the air-lift drilling method and to 110.00 m below GOK using the RKR core drilling method.
Sinking the test well 1 for the planned new waterworks using air lifting - drilling method with 800 mm Ø. After reaching the final depth of 107 m below GOK, wound wire filters made of stainless steel and solid pipes made of KV plastic made by Noresta as well as a DN 65 Norip monitoring pipe were installed. The filter section was then gravelled, a clay barrier with Quellon HD was poured and the annulus up to GOK was filled with a clay powder cement suspension. Finally, intensive sand removal and the power pumping test were carried out. A well shaft and the conveyor system will only be installed after the experimental operation has been completed.
NORD Bohr und Brunnenbau GmbH
Randersweide 1 | D 21035 Hamburg
Fon +49 40 735 956 – 30
Fax +49 40 735 956 – 40
E-Mail info(at)nord-bb.de